Below is how to migrate a project using the FIN Migrate tool. Only one project can be migrated at a time. If you have a FIN 4.5 project backup, but don't have FIN Stack 4.5 installed, look at step 2 below on how to migrate that without the FIN 4.5 service.
...
In our example below, we want to migrate our "demo" project. We select the "demo" folder under the db folder to migrate.
Note: If you have multiple projects and you want to migrate them at the same time, you can select the parent 'db' folder itself. That will migrate all the projects under the db folder at once.
The FIN 4.5 db folder path should be something like this but with your version: C:\Program Files (x86)\FIN Stack\FIN Stack 4.5.851\db
...
The user can then start the FIN Stack 5.0 service and be able to hit the project(s) via browser. Should be something like this for specific project "ip:port/finMobile/projName<projName>" or for host home "ip:port/pod/finStackMobileExt/home".html" (Update this later)
Thats it, the whole migration process has been completed and can check out the project or migrate another project following same process(s).