Schedule Weekly Events Fix

...

First the user will need to add the following trio through folio which will add the functions needed to fix the schedules.

View file
nameextraSchedule.trio

height250Once the user has the function, they can then run the following query in folio that will go through each schedule and fix them: readAll(schedule).toRecIdList().fixAllScheduleOverlap()

If the user only wants to apply this to a specific schedule instead of all, they would run the below query that includes the id of the schedule: fixScheduleOverlap(@1e8d9e6a-ff7041a7)

If the user wants to fix multiple schedules but not all. They would run the query below with the ids of each schedule (don't forget the brackets and they are comma separated): fixAllScheduleOverlap([@1e8da9fe-504bf575,@1e8d9e6a-ff7041a7])