Sync Bacnet Schedules

...

First, the user will drag the schedule point(s) to DB Builder.

Image RemovedImage Added

After that, the user needs to make the point writable and schedulable.

  • To do this enable the toggle bar: Blue = On & Grey = Off

Image Added

Make sure when making it writable, that the Write Path property matches the Cur Path. Image RemovedIf the Write Path is empty/blank, copy the Cur Path and paste it in the Write Path and hit Enter key to trigger Save button to save changes.

Image Added

Then the user will need to add the point to the schedule.

Image RemovedImage Added

After that, if the user doesn't already have a connTuning Policy on the connectorpoint, they will need to create one in folio and add it to the connector. You can learn how to do that here.

...

titlewriteSchedule Tag

...

need to create a tuning policy for the point that has "Write Schedule" enabled for it. This tuning policy should only be specific to these points. How to create one is explained here. Make sure to enable "Write Schedule" for it or manually add the writeSchedule tag on the policy!

With the above being completed, the schedule will now sync whenever there is a change of value.